Two crews, one machine, the same afternoon. A mechanical team is replacing a bearing on the conveyor, while an electrical team runs cabling through the same tray above it. Both teams lock out properly — and both teams are exposed. This scenario, minor or major depending on the day, is where coordination requirements in the standards earn their keep.

The rule behind the scenario is usually summarized in one line: when multiple employers or crews perform work on the same equipment, they must inform each other of their lockout procedures. The full version has more spine. Each group’s program must offer the others the same level of protection their own people get. Each crew applies its own locks, and no crew’s removal of its locks counts as permission to re-energize while another crew is still exposed. The primary employer — the one controlling the site — owns the coordination duty and does not escape it by pointing at the contractor.

The accidents that follow failed coordination have a pattern: both crews did their jobs correctly in isolation. The electrician finished, removed his lock, and re-energized the circuit — unaware the mechanical crew had a hand inside the housing two meters away. Everyone involved can honestly say they followed their procedure. That is what makes coordination failures unsettling: procedure-following individuals can produce a combined result that no individual intended.

Practical plants handle this with mechanisms rather than goodwill. A common lock box: every crew’s isolation keys go in, every crew’s locks go on the lid, and the machine stays dead until the lid empties. A pre-job coordination meeting where the sequence is said out loud — who is working where, who finishes first, who notifies whom before restoration. A single point of contact per crew, named in writing, so “let them know” has an actual recipient.

The communication must run both directions. It is not enough for the primary employer to inform contractors of its procedures; contractors must tell the primary employer what they are doing, and the handoff at job boundaries — finished, clear, removing locks — has to be explicit. Silence at that boundary is how the second crew gets started without knowing the first one is gone.

The underlying principle is older than the standard it is written into: no person’s safety may depend on information they were never given. Two crews that never spoke are one crew in the eyes of the machine.